Chapter 6 Self-Checks
Material and Distribution Requirements Planning
These questions follow the order of Chapter 6. Each of the first four groups checks one or more sections of the chapter, and the last group reviews the whole chapter, nervousness and the assumptions of requirements planning included. The “Self-check” buttons in the chapter lead to these groups. Nothing you answer is recorded.
Dependent Demand and the Bill of Material
1. True or False: whether demand for the deck belt is dependent is a property of the belt, so the belt should be planned the same way wherever it is stocked.
2. The manufacturer knows its deck schedule for the coming year and must plan the deck belts that go into the decks. Which approach does the chapter recommend?
3. In the deck assembly structure the bearing is used once in the deck assembly and twice in each spindle assembly, and its low-level code is 2. In what order are the five items planned?
4. Every item is planned lot-for-lot with nothing on hand. In period 9 the deck assembly releases 420 and the spindle assembly releases 520, while their planned order receipts in that period are 300 and 840. What is the bearing’s gross requirement in period 9?
The MRP Record and the Explosion
1. Which row of an MRP record is its output, the row the explosion calculation reads at the next level down?
2. The deck assembly is planned lot-for-lot with a lead time of one month and starts with 150 on hand and nothing on order. Its gross requirements in months 6, 7 and 8 are 40, 60 and 120. What are its net requirements in those three months?
3. True or False: if the deck assembly orders a fixed quantity of 500 and its printed record shows net requirements of zero in months 7 and 8, the lot sizing rule was asked to cover nothing in those months.
4. Suppose the spindle assembly’s lead time rose from one month to two, with every other lead time unchanged: deck assembly 1, belt 2, housing 2, bearing 3. How many empty months must the horizon have in front of the master schedule for nothing to be past due?
What Lot Sizing Does to the Level Below
1. True or False: part-period balancing makes the deck assembly’s receipts the lumpiest of the seven rules, with a variability coefficient of 1.5463, so it gives the most expensive plan for the structure.
2. With the deck assembly on least unit cost and every component lot-for-lot, the deck assembly releases 7 times and the bearing orders 12 times. A release costs the belt $300, the spindle assembly $250 and the housing $150 in setups, and a bearing order costs $100. What is the cost below the deck assembly?
3. A structure has ten thousand components, and nobody has measured their order costs. The end item’s setup is large and known. Which rules does the chapter defend for this structure?
Distribution Requirements Planning
1. The regions’ sales begin in period 5. The north sells 20 in period 5, the south 10 in period 5 and 20 in period 6, and the west 10 in period 5. Transit is one month to the north and west and two to the south, and every region orders lot-for-lot. What is the central warehouse’s gross requirement in period 4?
2. Under lot-for-lot at every region, the center sees a variability coefficient of 0.6334, against the 0.6191 of what the regions sell. What accounts for the difference?
3. When every region plans with Silver-Meal, the center sees demand with a variability coefficient of 1.3715. The regions sell a pattern whose coefficient is 0.6191. How many times as variable as what the regions sell is the demand the center faces?
Review of the Whole Chapter
1. A planner wants one order of the deck belt to stay where it is, whatever the next run of the explosion computes, while the rest of the plan stays free to move. Which device does the chapter name for this?
2. True or False: a revision to the master schedule eleven months out can only move orders that are placed far in the future, since every level plans its own items later than the level above.
3. Under lot-for-lot the bearing’s record asks for 1,980 bearings to arrive in period 8, although no deck assembly is ever built in a quantity approaching that. Nothing in the explosion asks whether that many can be made or received. Which assumption of requirements planning does that rest on?
4. The distribution network’s cumulative lead time is four months: two months of transit to the south and two months for the center’s supplier. Suppose the horizon has only three empty months in front of the regions’ sales. How much is past due, and where?