Chapter 9 Self-Checks
Periodic Review and Other Policy Forms
These questions follow the order of Chapter 9. Each of the first four groups checks one or more sections of the chapter, and the last group reviews the whole chapter, the many-item allocation, the updating of parameters and the choice of a model included. The “Self-check” buttons in the chapter lead to these groups. Nothing you answer is recorded.
The (R, S) Policy and Its Level
1. Under an \((R, S)\) policy the storekeeper raises the position to \(S\) at the review at time \(t\). Until when must the stock committed at that review cover demand?
2. The transformer has Poisson demand at \(\lambda = 45\) units a year and is reviewed every two weeks, so a review interval holds \(\lambda R = 45(2/52) = 1.7308\) units of demand on average. How many orders a year does the storeroom place?
3. The transformer is reviewed monthly with a two month lead time, and the critical ratio is \(b/(b+h) = 0.90\). Which distribution must the ratio be applied to, and which level does it give?
The Review Interval and the Price of Not Watching
1. The transformer has \(k = \$220\) an order, \(h = \$950\) per unit per year and \(\lambda = 45\) units a year. What review interval does \(R^{*} = \sqrt{2k/(h\lambda)}\) recommend?
2. True or False: when the transformer moves from its best continuous policy, \((r, Q) = (8, 7)\), to its best periodic policy, \(R = 0.120\) year and \(S = 15\), the whole premium of $961.77 a year is the holding cost of extra safety stock.
3. A storeroom is free to set its own review calendar for an item, and demand arrives one unit at a time. Which calculation applies?
Lumpy Demand
1. The fuse cutout is drawn in job lots of 1, 2 or 4 units with probabilities 0.40, 0.40 and 0.20, at \(\lambda_{e} = 400\) lots a year. Suppose the supplier’s lead time grows to four weeks. What is the variance of lead time demand, in units squared?
2. True or False: demand that arrives in lots raises the mean lead time demand above \(\lambda L\), at the same demand rate \(\lambda\).
3. The storeroom runs the cutout at \((r, Q) = (25, 75)\) and reports its ready rate, 0.9060, as its service level. What proportion of the cutouts asked for is filled from the shelf on arrival?
4. The cutout is watched continuously and drawn in lots, and the supplier sells it only in whole cartons of 25. Which policy should the storeroom compute?
The (s, S) and (R, s, S) Policies
1. The cutout’s lots of 1, 2 or 4 give an expected undershoot of \(E[U] = 0.8\) units, and demand is 800 units a year. The storeroom approximates the \((s, S) = (38, 48)\) policy by an \((r, Q)\) policy. What order frequency should the approximation use?
2. True or False: Scarf’s theorem tells the storeroom the values of \(s\) and \(S\) to use.
3. The transformer’s demand arrives one unit at a time, Poisson at 45 a year, and the item is put on an \((R, s, S)\) policy reviewed every two months, so a review interval holds \(\lambda R = 7.5\) units on average. The spread \(S - s\) is wide. What is the expected undershoot?
Review of the Whole Chapter
1. The utility adopts the cutout’s backorder cost, \(b = \$287.50\) per unit per year, across the whole storeroom. The transformer’s holding cost is \(h = \$950\) per unit per year. What ready rate does the critical ratio \(b/(b + h)\) then imply for the transformer?
2. The transformer’s forecasting system works monthly and reports a smoothed mean absolute deviation of \(\mathit{MAD}_{t} = 1.55\) units. The lead time is two months, and the forecast errors are strongly autocorrelated, so you take the scaling exponent \(\eta = 1\). What is \(\sigma_{D(L)}\)?
3. A running system’s forecast of the demand rate is revised every month. Which parameter should be recomputed on that cycle?
4. Ground rods are drawn by crews in bundles, the record is watched continuously, and the storeroom orders up to a level whenever the position falls to its reorder point or below. Which calculation applies?
5. True or False: because the conversion from the mean absolute deviation to \(\sigma_{D}\) assumes normally distributed forecast errors, lead time demand should then be modeled as normal.