Explore: An (r, Q) Policy for Your Own Item

Chapter 8, Continuous Review Systems

This page evaluates and optimizes an \((r, Q)\) policy for an item you describe, with the exact methods of Chapter 8. It is the general form of the transformer’s explorer, and it starts from the transformer’s values; Reset returns to them. Enter your item’s costs and its lead time demand, and the page finds the optimal policy by Algorithm Optimize_rq, checks it against the bounds that are known before solving, and evaluates any policy you choose beside it.

The page runs in your browser and records nothing. Its formulas are a restatement in JavaScript of the book’s code, and they are tested against that code on a range of items, from a slow mover with a lead time demand of a few units to a fast mover with a thousand.

What This Page Assumes

The page computes exactly, and it can do so only for the model below. Read these before you rely on a number from it.

  • The system. Continuous review, an \((r, Q)\) policy, demand that arrives one unit at a time, and unmet demand backordered. Orders are received in the sequence they were placed.
  • The costs. A fixed cost \(k\) per order, a holding cost \(h\) per unit per year, and a backorder cost \(b\) per unit per year owed. A cost \(\pi\) per unit short is a different model, and this page does not offer it.
  • Lead time demand. It is a discrete count, Poisson or negative binomial. The family follows the chapter’s rule on the variance to mean ratio. A ratio within 0.05 of one is Poisson at the mean, and the variance you entered is replaced by the mean. A larger ratio is negative binomial, matched to both moments. A ratio below one is refused, since neither family fits it.
  • The bounds. The mean lead time demand must lie between 0.1 and 5,000 units, and the variance to mean ratio must be at most 50. Outside them the tables the page builds become too long for a browser.
  • The service measure. The page reports the ready rate, not the fill rate. The two are equal when demand arrives one unit at a time in a Poisson process, as it does when you build the lead time demand from a demand rate and a lead time below. If you enter a variance from data whose demand arrives in bursts, the fill rate can be lower than the ready rate.
NoteFor anything else, use the software

Demand in lots, a gamma or another family, a service target, the classical approximation, or a cost per unit short are all in the code the chapter teaches, in Using the Software, and the chapter’s workbook covers the approximation and the service targets.

Your Item

The first plot is the cost against the reorder point, with the order quantity held at your \(Q\). The red dot is your policy.

The second plot is the ready rate against the reorder point at the same \(Q\), with your policy as the red dot.

The third plot is the least cost at each order quantity, from the steps of Algorithm Optimize_rq continued past the optimum. Each point is the best reorder point for that \(Q\). The red dot is your \(Q\).

Things to Try

  1. Leave the transformer’s values and press Use the optimal policy. The page finds \(r = 8\) and \(Q = 7\) at $7,225.15 a year, the answer of the chapter’s trace of Algorithm Optimize_rq, and the checks pass.
  2. Set the standard deviation of the lead time to 1 month. The lead time demand becomes negative binomial with variance 21.5625, and the optimum moves to \(r = 10\) and \(Q = 8\) at $11,079.73.
  3. Set the ordering cost to 0. The optimum is one for one, \(Q = 1\) with \(r = 10\), which is the base-stock level \(S^{*} = 11\).
  4. Try a fast mover: \(\lambda = 6{,}000\) a year, \(k = \$27.50\), \(h = \$0.85\), \(b = \$8.50\), and a lead time of 2 weeks. The optimum orders 655 at a time, and the cost lies just inside its upper bound.
  5. Enter a lead time demand directly with a variance below its mean. The page refuses it and says why.