Explore: An MRP Record of Your Own

Chapter 6, Material and Distribution Requirements Planning

This page computes the six rows of one item’s record, as Chapter 6 defines them, for requirements you enter: it nets them against the opening stock and the scheduled receipts, lets a lot sizing rule decide the planned receipts, carries the balance, and offsets the receipts by the lead time. It starts from the deck assembly’s record; Reset returns to it. The page runs in your browser and records nothing. Its formulas are a restatement in JavaScript of the book’s code, and they are tested against that code.

\[ \begin{aligned} \mathit{NR}_t &= \max\left(\mathit{GR}_t + \mathit{SS} - \mathit{SR}_t - I_{t-1},\; 0\right)\\ I_t &= I_{t-1} + \mathit{SR}_t + \mathit{POR}_t - \mathit{GR}_t\\ \mathit{Rel}_{t-L} &= \mathit{POR}_t \end{aligned} \]

What This Page Assumes

  • The requirements. Gross requirements known for every period of the horizon, one number per period, separated by commas or spaces. Zeros are allowed. At most 60 periods. Scheduled receipts are entered the same way, from period 1; a blank means none, and a shorter list means none after it.
  • The item. An opening stock \(I_0\), a safety stock \(\mathit{SS}\), and a lead time \(L\) of whole periods, 0 or more. A receipt the lead time would release before period 1 is reported as past due and released nowhere.
  • The rule. Lot-for-lot, any rule of Chapter 5, or a fixed order quantity. A rule of Chapter 5 is applied to the net requirements before lot sizing, from the first period that has one.
  • The costs. A fixed cost \(k\) per order and a holding cost \(h\) per unit on hand at the end of a period, both the same in every period.
NoteFor anything else, use the software

Several items in a bill of material, explored level by level, are on the deck structure’s page. Structures of your own, allocations, and costs that change by period are in the code the chapter teaches, in the chapter’s Using the Software section, and the chapter’s workbook computes the same record cell by cell.

Your Record

The plot is the projected on hand at the end of each period, as blue bars, with the gross requirements as red dots. Under lot-for-lot with nothing on hand the bars are flat at the safety stock; a rule that batches builds them up and draws them down.

Things to Try

  1. The starting record is the deck assembly’s: five empty months, then the twelve-month schedule, lot-for-lot with a lead time of one month. It places 11 orders for $5,500, the balance never leaves zero, and the releases are the schedule pulled back one month.
  2. Turn on Leave out the netting. The balance falls to \(-1,840\), the whole year’s requirement: correct arithmetic and a useless plan.
  3. Set the opening stock to 60. In period 6 the net requirement is zero and 20 units carry into period 7, whose net requirement falls to 40. The record places 10 orders, and the 60 units carried for five months and the 20 carried for one cost $1,152.
  4. Set the opening stock back to 0 and the safety stock to 20. The record asks for the 20 in period 1, which the lead time makes past due, and then holds 20 in every period, at $1,224 of carrying.
  5. Choose the fixed order quantity of 500. Compare the last two rows: in periods 7 and 8 the rule was given 60 and 120, but the printed net requirements are zero, because the 500 received in period 6 covers them. That is the chapter’s two readings of the net requirement.
  6. Choose Wagner-Whitin. The record places 9 orders for $4,860, the deck assembly’s figure in the chapter’s comparison of rules.
  7. Set the lead time to 6. The receipt due in period 6 would be released in period 0, so 40 units are past due: five empty months are not enough lead-in for a lead time of six.

Check What You Found

Check what you found

1. An item is planned lot-for-lot with a safety stock of 20, nothing on hand, nothing on order, and a lead time of one month. Its first gross requirement falls in month 6. In which month does the record first ask for the 20 units?