Explore: The Deck Structure, Exploded

Chapter 6, Material and Distribution Requirements Planning

This explorer runs the explosion of Chapter 6 on the mower deck assembly and the four items that go into it, with the lot sizing rules in your hands. Choose a rule for the deck assembly and another for every component, and watch what the end item’s choice does to the requirements, the orders and the costs below it. The structure is the chapter’s: one belt, two spindle assemblies and one bearing per deck, and one housing and two bearings per spindle assembly, so that the bearing has two parents.

Recall that a component’s gross requirements are its parents’ planned order releases times the quantity per, summed over the parents:

\[ \mathit{GR}_{jt} = \sum_{i} q_{ij}\,\mathit{Rel}_{it} . \]

The page runs in your browser and records nothing. Its formulas are a restatement in JavaScript of the book’s code, and they are tested against that code under every pairing of the two rules. For one record with inputs of your own, use the record explorer.

The Structure

The record below is the one you chose to show, with the periods across the columns as the chapter draws it. Notice that every release sits one lead time to the left of its receipt, and that a component’s gross requirements are its parents’ releases, not their receipts.

The plot holds the rule on the components fixed at your choice and tries every rule on the deck assembly. Each bar is what the deck assembly costs, and its extension is what the components cost beneath it; the bar outlined in red is your rule. Notice that the rule cheapest at the deck assembly is not the rule cheapest for the structure.

Things to Try

  1. Start with every item on lot-for-lot. The plan costs $14,500, all of it setup: $5,500 at the deck assembly and $9,000 below it. Show the bearing’s record: its gross requirements are 160, 280, 540, 1,320 and so on from period 4, two streams added on different offsets.
  2. Put Wagner-Whitin on the deck assembly. It costs $4,860 there, the least any rule can, and the structure costs $12,360. The adjusted economic order quantity costs $5,588 at the deck assembly and $11,488 for the structure, $872 less.
  3. Put part-period balancing on the deck assembly. The variability coefficient rises to 1.5463, the lumpiest of the seven, yet the structure costs $11,544, among the cheapest: the order count, 7, explains the cost below, and the variability coefficient does not.
  4. Keep the adjusted economic order quantity on the deck assembly and put Wagner-Whitin on every component. The structure costs $11,023.20, and least unit cost on the deck assembly now does better, at $10,914.40.
  5. Return every rule to lot-for-lot and cut the empty months to 3. The bearing’s lead time of 3, below a spindle assembly and a deck assembly of 1 each, needs 5, so 520 units are past due; at 4 months, 160 are.

Check What You Found

Check what you found

1. With every component on lot-for-lot, Wagner-Whitin costs $4,860 at the deck assembly, the least any rule can, and the adjusted economic order quantity costs $5,588. Yet the structure costs $12,360 under Wagner-Whitin and $11,488 under the adjusted economic order quantity. Why?